From: Robert Lanigan [rlanigan@MIT.EDU]
Sent: Friday, January 16, 2004 8:58 AM
To: Chris Hill
Cc: 'Robert Lanigan'; 'andrew Bonvie'; marco Gomes
Subject: RE: 10g campus connections
Chris,

        The following estimates are based on present material and labor costs and no contingency is built in. 
These estimates could change with changes in material and/or labor costs. A 10% contingency is recommended.

The material lead time is 5 work days and the installation will be approximately 2 weeks. If you choose to
have these circuits built we would like to have the length , loss budget of the equipment you plan to deploy.

        Marco Gomes helped me with this information, He will be working with me on the project should you
move forward with it and Marco or myself can be contacted for any further assistance.

Thank You
Bob Lanigan


For site Layout 1 can you get me cost (upfront and recurring) and lead-time
information for the following single mode fiber link (the <-> symbol below)
options

 option a

   site 1 <-> site 4----------$4700.00
   site 2 <-> site 4 ---------$550.00
   site 3 <-> site 4----------$2500.00
                        Total---------------$7750.00  one time installation cost
                        Total ---------------$750.00 monthly costs
 option b

   site 2 <-> site 4----------$3800.00
   site 3 <-> site 4----------$3500.00
                        Total--------------$7300.00 one time installation cost
                        Total--------------$500.00 monthly costs

  For site Layout 2 I'd like estimates for a single scenario
 
   site 1 <-> site 4-----------$4700.00
   site 2 <-> site 4-----------$2500.00
   site 3 <-> site 4-----------$2500.00
                        Total---------------$9700.00 one time installation cost
                        Total---------------$750.00 monthly costs


At 02:33 PM 1/14/2004, Chris Hill wrote:
Hi Bob,

 It was good to talk to you this morning.
 Here is a summary of the options I would like to get estimates on cost and
lead-time and any other issues that you think are relevant. It would be very
useful to have rough estimates in the next couple of days if possible.

Thanks

Chris Hill

Background
==========

 We are looking to install four cluster facilities at four sites on campus.
Each cluster will have an Enterasys N7 switch with one or more 10g
interfaces. The interface optics is 1310nm SMF that has an SC connector. The
interface between this facility and the wider world will be from a
connection through to the main Stata fabric.

 There are two possible site layouts that we are looking at:

Layout 1

  site 1: 54-1727
  site 2: 54-527
  site 3: 48-208
  site 4: stata mezzanine level

Layout 2

  site 1: 54-1727
  site 2: E34-500
  site 3: 48-308
  site 4: stata mezzanine level

 Can you give me estimates for configurations involving these different site
possibilities as follows:

 For site Layout 1 can you get me cost (upfront and recurring) and lead-time
information for the following single mode fiber link (the <-> symbol below)
options

 option a

    site 1 <-> site 4
    site 2 <-> site 4
    site 3 <-> site 4

 option b

    site 2 <-> site 4
    site 3 <-> site 4

  For site Layout 2 I'd like estimates for a single scenario
 
    site 1 <-> site 4
    site 2 <-> site 4
    site 3 <-> site 4

My contact information is

 Chris Hill, EAPS
  room: 54-1515
 email: cnh@mit.edu
   tel: 617 253 6430
 

> -----Original Message-----
> From: Robert Lanigan [mailto:rlanigan@MIT.EDU]
> Sent: Tuesday, January 13, 2004 3:50 PM
> To: Chris Hill
> Cc: andrew Bonvie
> Subject: Re: 10g campus connections
>
> Chris,
>
>          Lets talk on the phone first, I'd like to hear your
> needs and do some research before we meet.
>          I'll be in my office most of the morning----253-0312
>
>                  My cell is 617-201-3628
>
>
> Thanks
> Bob
>
>
>
> At 03:21 PM 1/13/2004, you wrote:
> >Bob,
> >
> >  Jack Costanza referred me to you to discuss some fairly imminent
> >plans we have for connecting several sites around campus to a
> >concentration point in Stata. Some of these sites have fiber
> in place
> >that will need rerouting from
> >NE43 to Stata, other sites we are thinking about have no
> fiber to them
> >as far as I know. Jack says you are the man to talk to about this.
> >
> >  Would it be possible to meet up sometime tomorrow - Wed,
> Jan 14, or
> >at least talk on the phone.
> >
> >Thanks,
> >
> >Chris
>